Cedenco Hawkes Bay Relocation. |
|
|
IMS was contracted to relocate an existing IQF freezing plant from Hawkes Bay to their main factory in Gisborne. This involved decommissioning of the the existing switchboard and control panel and upgrading for installation.The Sabroe compressor was overhauled along with the liquid pump, new and existing pipework to the freezer tunnel, and a complete overhaul of the tunnel itself.
|
|
| |
|
|
|
|